9A Paving Update
Release Date: May 29, 2020
***UPDATE 5-29-2020***
All-
Week of 5-31 thru 6-4
NO WORK
***MILLING & PAVING WILL BEGIN 7/6*****
*** Welcher Avenue Exit will be closed Monday 7/6 for milling & paving, detour in place to Montrose Exit ***
Milling & paving will begin at the northern end of the project, beginning with the rt 9 off ramp & welcher ave. they will then proceed south & then turn around back north. Day 2 (Wednesday 7/7) there will be no parking on the shoulders on the southbound side. Again, I ask for assistance in this matter. If inclement weather all work will shift a day.
One lane will always be open, alternating traffic with flaggers will be utilized.
All work weather dependent and will shift accordingly.