Update- Albany Post Road / Route 9A Paving
***UPDATE***
Albany Post Road / Route 9A Paving
From the NYSDOT Engineer in Charge
Week of 5-26 thru 5-28
Nightwork Sunday – Thursday 8:00pm-6:00am
Basin work will continue. Rail & gutter cleaning will continue. No Parking signs installation near Bleakley.
One lane will always be open, alternating traffic with flaggers will be utilized.
All work weather dependent and will shift accordingly.
Week of 5-31 thru 6-4
Nightwork Sunday – Thursday 8:00pm-6:00am
***MILLING & PAVING WILL BEGIN 5/31*****
*** Welcher Avenue Exit will be closed Sunday 5/31 for milling & paving, detour in place to Montrose Exit ***
Milling & paving will begin at the northern end of the project, beginning with the Rt. 9 off ramp & Welcher Ave. Contractor will then proceed south & then turn around back north. Day 2 (Wednesday 6/1) there will be no parking on the shoulders on the southbound side.
If inclement weather all work will shift a day.
One lane will always be open, alternating traffic with flaggers will be utilized.
All work weather dependent and will shift accordingly.